FRETTENHAM SERVICE STATION

Client: Frettenham Service Station

Duration:6 Weeks

These works consisted of the demolition of the current structure and installation of a new engineered base, including access pit for their new modern MOT bay.

  • Complete demolition of structure and removal of all footings and pads. The area was left level with a hardcored base

  • Demolition of existing MOT bay including all bases and foundations. Area was left clean and level ready for the construction of the new pad.

  • Construction of new concrete pad foundation

  • Construction of new pit within structure to specifed lengths a length and steps at the far end.

  • Formation of pockets within the pad structure to receive scissor lift, brake testing unit and shaker plates